Completion date: September 24, 2016
Location: Philadelphia, PA
The challenges we faced were that, because it was a church, we had to install the job on a Saturday, and the pump dig was extremely hard because it was all stone, but we got it done.
To address this, Project Manager Steve proposed a GrateDrain drainage system with a new Grate Sump on the one wall where the water was seeping in. We also installed a 4-foot-high vapor barrier to protect against wall leaks and direct any wall seepage into the perimeter drainage system. Now the church can use their lunch room again.